Where it is available, Section 203 is one of the most effective ways of managing rights of light risk, however it is often considered too late in a scheme to be used.
It does not apply to every site, and a developer cannot invoke it on their own. Where it is available, however, it changes the basis of the negotiation, because it removes the adjoining owner’s ability to stop the scheme, which is the main source of their negotiating position.
The problem it solves
A right of light is a private property right, and the primary remedy for interference with a property right in English law is an injunction. It is the injunction, rather than the compensation, that gives rights of light its commercial weight.
A neighbour who can credibly threaten to stop a development is, in practice, negotiating over the value of the developer’s programme as well as the value of their lost light. The second figure is usually much larger, and it is set by how much the scheme is worth to the developer rather than by how much light the neighbour has lost.
Section 203 breaks the link between the threat of an injunction and the price of a release.
What it does
Section 203 of the Housing and Planning Act 2016 replaced the earlier provision at Section 237 of the Town and Country Planning Act 1990.
Where land has been appropriated for planning purposes by a qualifying authority, and the statutory conditions are satisfied, building or maintenance work carried out on that land may proceed even though it interferes with a third party right such as an easement of light.
The right itself is not extinguished. What changes is the remedy. The neighbour retains a claim, and that claim is for compensation, assessed broadly by reference to the diminution in value of their property. What they no longer have is the ability to obtain an injunction.
Practically, the settlement conversation moves from “what will it take to let this scheme proceed” to “what has this cost you”. Those are different questions and can produce materially different figures, particularly on a constrained central site.
Who can use it
The power belongs to qualifying authorities, not to developers. A private developer cannot appropriate its own land.
The route that is used in practice involves a local authority, or another qualifying body such as certain public corporations, acquiring or already holding the land, appropriating it for planning purposes, and then disposing of it to the developer. The Section 203 protection passes with the land to the successor in title.
In practice, the developer’s main task is persuading a public body that this is an appropriate use of a statutory power, on a scheme that delivers something the authority wants.
What an authority will want to see
Every authority approaches this differently and you should take advice specific to the body concerned. Broadly, expect to have to demonstrate:
- That the development delivers a clear planning benefit, which usually means the things sitting in the local plan: housing numbers, affordable provision, regeneration, employment floorspace.
- That planning permission is in place or is realistically forthcoming.
- That reasonable attempts have been made to deal with affected parties directly. Section 203 is not intended as a substitute for negotiating.
- That the compensation liability is understood, quantified and secured, so the authority is not exposed.
- That the statutory conditions are met on the facts of the site.
The last two are where our work sits. An authority is being asked to take a decision with a compensation liability attached to it, and the quality of the technical evidence behind the exposure figure has a significant bearing on how comfortable they are.
Why it has to start early
Section 203 involves a process that takes time. It requires the authority to form a view, a decision that will normally require a committee, legal agreements between the parties, and an appropriation that has to be properly made.
Schemes that begin exploring it once neighbours have already instructed solicitors are in a much weaker position. The authority is being asked to act in the middle of a live dispute rather than as part of an orderly delivery strategy, and the timetable rarely fits the developer’s programme.
The route is not open simply because a scheme involves a council or another public body. It depends on how the land is held, whether a qualifying authority has acquired or appropriated it and on what basis, whether planning permission is in place for the works, and whether the works relate to the purpose for which the land was acquired or appropriated. Those are legal questions on which site-specific advice is needed. Where the land history suggests the conditions might be met, it is worth testing at feasibility rather than at pre-construction.
Where it fits alongside everything else
Section 203 is one of several routes, and most schemes use more than one. The others are designing the injury out, negotiating releases, placing insurance, and cutting back the element causing the injury.
The point of taking advice early is to establish which of them are realistically open, because their availability changes as a scheme progresses. An approach to neighbouring owners can affect what insurance cover is available and on what terms, so the sequence should be coordinated with specialist insurance advice from the start. Section 203 involves a process that takes time, and becomes harder to accommodate once the programme is well advanced.
We set out how these fit together on our rights of light page. If you have a site where a public body has an interest, it is worth a conversation early rather than late.
This is general commentary rather than legal advice. Whether the statutory conditions are met on a particular site is a legal question, and one that needs site-specific advice.
Sources
- Housing and Planning Act 2016, section 203. Power to override easements and other rights.
- Housing and Planning Act 2016, section 204. Compensation for overridden easements.
- Town and Country Planning Act 1990, section 237. The predecessor provision.
- Compulsory Purchase Act 1965, sections 7 and 10. The basis on which compensation is assessed.