Great North Leisure Park, North Finchley
Internal daylight and overshadowing assessment for the redevelopment of an 11-acre leisure park in North Finchley, delivering around 1,485 homes, a new leisure centre and lido.
A 185-room aparthotel replacing a 1990s office building on the corner of Wyvil Road and Trenchold Street, assessed for daylight, sunlight and overshadowing against its neighbours and the Wyvil School playground.
Ground floor and ten upper storeys
Construction due to start Q4 2026
Resolved to grant September 2025
Wyvil Court is a four-storey office building dating from the 1990s, on the corner of Wyvil Road and Trenchold Street in Vauxhall. Vacant since December 2020, it is set to be replaced by a 185-room aparthotel designed by EPR Architects for Wyvill Road LLP and Citygrove. The approved scheme comprises a ground floor and ten upper storeys, with a publicly accessible reception, co-working space, café bar and pantry shop at ground level, alongside improvements to the public realm on Trenchold Street. It is the final plot within the Lambeth Local Plan site allocation 11 to come forward for development. The hotel is scheduled to open in the third quarter of 2028.
The site presented significant daylight and sunlight constraints. Keybridge House rises to 20 storeys directly along the northern and eastern boundary, with residential windows and deep overhanging balconies overlooking the site. To the west, 12–20 Wyvil Road is under construction and rises to 36 storeys. Between the two is the Wyvil School playground, enclosed on three sides and partly built over, which already receives limited direct sunlight. Redevelopment would affect these neighbouring properties and outdoor spaces, so the assessment needed to establish the extent of those effects and whether they were acceptable in the local context.
MDX Surveyors was appointed at the outset and worked alongside EPR Architects through pre-application discussions with Lambeth. We tested successive building massing options, including reductions in height of between one and five storeys. Our analysis showed that these reductions would provide very little measurable benefit to neighbouring buildings or the playground. This evidence helped the design team support the proposed height and massing through the planning process.
MDX prepared a full daylight, sunlight and overshadowing assessment with reference to the BRE Guidelines (2022), covering Keybridge House, Gilbert House, Wyvil Primary School and the school playgrounds. An alternative baseline assessment compared the proposal with a notional building matching the height and massing of its neighbours. This showed that the proposed scheme performed materially better for Keybridge House. The assessment also explained how the position of neighbouring windows close to the site boundary contributed to the larger percentage reductions in light identified at some windows.
For the overshadowing assessment, we extended the analysis beyond 21 March to examine sunlight hours at ground level throughout the year. The lower playground falls below the BRE recommendation under both the existing and proposed conditions, with additional shadowing from the scheme limited to short periods around the equinoxes. The design team engaged directly with Wyvil School to understand how the playground is used and took this into account when refining the building massing.
Our reporting explained the technical findings clearly for planning officers and decision-makers, considering them in the context of Policy Q2 of the Lambeth Local Plan, Policy D6 of the London Plan and the National Planning Policy Framework (NPPF), including its provision for flexibility in dense urban locations.
Lambeth resolved to grant planning permission in September 2025, and consent was issued later that year. Construction is due to start in the fourth quarter of 2026. Our assessment helped the planning authority consider the daylight, sunlight and overshadowing effects in the context of the surrounding development, supporting the case for the approved scheme.
Internal daylight and overshadowing assessment for the redevelopment of an 11-acre leisure park in North Finchley, delivering around 1,485 homes, a new leisure centre and lido.
A co-living redesign of a consented scheme, showing no perceptible daylight loss to neighbours over the consent, and 89% of studios meeting the daylight target.
Send us the site and the massing. We will tell you what the light position looks like and whether it needs work.